Wednesday, April 29, 2026

Volunteers Use up April Weekends(and a few Weekdays) to take on essential Shipyard Projects.

 March 28th.  The day after the Masts came down.  Big Plans. and the largest gathering of Volunteers since the start of this Shipyard period. Now there was something concrete to do, mainly maintain the masts.  

Once the Coast Guard released the masts from their inspection, Volunteers were almost rubbing their hands with glee. We expected to be an extended week or so of just sanding down to wood, the entire 76 feet of those giant spars. (The white masthead, and table on the opposite end would be sanded/scuffed and given two new coats of gloss white.)  That was not to be the case. 

Media Expert and Volunteer Rebecca Poynten-Murray
 works a rag wet with Borax solution
 over remaining grimy spots on the foremast.
Rigger Steve Geering listened patiently to our plan, then proposed an alternative: "Borax".. the same thing a few of us older generations remembered in commercials of the classic western TV series, "Death Valley Days."  We didn't know that stuff was still around, Obviously new products had to have long ago replaced it's supposedly effectiveness.  Just a big scoop of the white crystal granular powder in a sea bucket of relatively clean water and a super-heavy duty Scotch scrubby, enabled a few volunteers to basically wipe down the entire mast, rinse off their scrubbies and the mast, and let her dry out for rest of the day. By end of the first week in ApriI. In one weekend, Both masts were cleaned of their solid black grime, and stood ready to receive their next coats of ... something.  

As that activity was starting up, Rigger Steve Geering had stripped all the remaining standing rigging, and running rigging gear from the masts.  Shrouds were laid out along side, and ratlines/ratboards separated. Where possible, blocks were unrove and separated out to be serviced, lubricated and repainted. 

Another innovation, was laid out.  In the previous two weeks, a discussion had ensued with Bryan Oliver voicing the history up to this point,, the simple wiping on of two coats of linseed oil for its dual qualities of preservative penetration, and UV protection. followed by gobs of Vaseline for lubrication under the mast hoops. Problem was, it required reapplication annually, and the surface accumulated sufficient dust and grime to form the ugly black patina all over the wood. 

Again, Rigger, Steve Geering posited an alternative; the application of a wood oil, without the stickyness of Boiled Linseed oil, and twice the service life. Conveniently a similar discussion had earlier been resolved regarding the coatings of the brightwork on deck- the railings, hatches, and sapele mahogany trim. 

This year we were implementing a favorite of Board Member, Hank Hofford. Brazil Nut Oil. Unfortunately, three people, Bryan Oliver, and Adam Reed were internet search, having no luck, and time was running out. A substitute, "Penofin" was recommended by someone, some quick research was done, it was available, and so 5 gallons was ordered. 

Rot discovered in the Mainmast head.
 Thanks to Rigger Steve, and Shipwright Ray,
 this section was cut out, and a new section "scarfed back in. 

As it was being applied. Sam Gervais announced the finding and ordering of copious quantities of Brazil Nut Oil 5 gallons. It arrived shortly afterwards, and on recommendation by Steve the Rigger, volunteer, Doug Hartley, Tony Marchesani, and Nick Swarts went to work with paint rollers, applying first one, then two more coats over both masts. Over two weeks, allowing for  the product to penetrate the wood between coats

Piles of blocks down-rigged from the masts
  awaiting some loving care.
Volunteers weren't only maintaining masts. Equally important was all the running rigging gear down rigged, and now, after ten years finally available for close inspection and servicing. Ken Fonville organized a small group of volunteers to transport over a two week period, 24 blocks to the Low Country Maritime Center, where they disassembled each into major components, the sheave, sheave pin, block itself, and sometimes 'strop." Each block was inspected for wear. Sheaves and pins were lubed with grease, and the blocks received a new coat of 'Sandtone' paint.



Another 24 blocks were still up-rigged,
and  unavailable for maintenance.
They will be maintained in place,
 or down-rigged separately.



Shipwright Rachel Berquist of the  Lowcountry Maritime School
 supervises the setting up of the ship's rudder,
which will become her project of "healing."




 